PROJECT SCHEDULE 

                                                        * Comprehensive Agreement executed:                                                         July 12, 2011
                                                        * Pre-Grading Construction Start:                                                                 September 2011
                                                        * Substantial Completion Classroom Wing/Administration:                  July 2013
                                                        * Substantial Completion Remainder of Building:                                     August 2013
                                                        * Final Completion:                                                                                          November 2013
 

  

                        